Selected ESAC assignment · Abu Dhabi, UAE
Beach rehabilitation design review in Abu Dhabi
A coastal works package needed an independent technical review of its proposed breakwater and sediment-control design alongside an environmental route for the construction activities.
← ESAC Water projects
The project question
What needed technical resolution?
Beach nourishment, a breakwater gap and sediment-control features had to work as one coastal scheme. The contractor's calculations and design assumptions needed checking before the package could advance through engineering and environmental review.
Our contribution
Independent checks with traceable comments
- Reviewed the contractor's design documents and supporting calculations.
- Reran selected GEO5 slope-stability models to examine the critical slip surfaces.
- Issued written reservations and requests for clarification to the contractor.
- Prepared draft environmental management and authority briefing material for the proposed works.
Documented outputs
What ESAC issued and prepared
- Written design-package review and technical reservations sent to the contractor
- Technical note recording independent GEO5 model checks
- Draft construction environmental management plan and pre-application briefing material
Assignment status
What the records show
ESAC sent the design review and reservations in November 2026. The environmental plans in the reviewed folder are drafts. The available records do not establish design acceptance, environmental submission, permit issue or completed construction.