Selected ESAC assignment · Abu Dhabi, UAE
Marine edge protection design in Abu Dhabi
A waterfront extension required a seawall design that connected marine loading, ground conditions, construction materials and the existing edge.
← ESAC Water projects
SectorWaterfront and marine infrastructure
ESAC's roleMarine design consultant to the contractor
Documented stageDesign report and signed design confirmation; later review comments
The project question
How should the new seawall meet the existing edge?
The design had to account for the seabed profile, ground capacity, water levels and vessel-generated waves while maintaining a workable connection to existing marine infrastructure.
Our approach
Connect the inputs to the design checks
- Reviewed available bathymetric and geotechnical information.
- Established design water levels and the applicable marine loading cases.
- Checked wall stability, bearing and settlement for the proposed seawall section.
- Documented the design basis, materials and construction interface for review.
Documented outputs
A reviewable marine design package
- Detailed seawall design report
- Signed ESAC marine design confirmation
- Supporting design calculations and coordination records
Assignment status
What the records show
The ESAC design report and signed confirmation establish its design role. A subsequent reviewer response was satisfactory on basic information but raised material criteria and further approval conditions. The available records do not establish final authority approval or construction completion.